Over the past year all of our stakeholders have talked a great deal about the overall timeline and specific schedules needed for project completion—construction schedule, relocation schedule, schedule for furniture, and others. Along with team members Roberto Rengel and Rose Barroilhet, I attend the bi-weekly construction progress meetings so we can keep Human Ecology-specific deliverables on task and coordinate with JP Cullen. At these meetings schedule details are hammered out with the contractor for testing and balancing, when the building is to be cleaned, coordination with campus for fiber optics, and so on.
A major milestone is "substantial completion," the point in the project where the state (remember it's the state, not the campus, that holds the contract) in consultation with the campus, determines that the contractor is just about —but not quite—finished. The architect and campus develop a "punch list" of items that the contractor is still required to complete, but the progress of preparing to occupy the building may continue to move forward.
The time from substantial completion until the start of furniture delivery is busy and many tasks are executed. The internal systems (heating, ventilating, etc.) are tested and balanced, punch list items and technology interface with equipment continues, and many, many more details are confirmed. Furniture delivery—a massive undertaking coordinated and led by campus—won't begin until after this period of testing is complete. And having seen the draft schedule for furniture delivery and installation, I can verify this is a complex plan involving access to the Human Ecology loading dock, coordinating which vendors have access to the building elevators and for how long, and when the semi-trucks are allowed on campus.
The bottom line? The academic departments (CS, DS, HDFS, and IS) will be the first to move into the new building starting May 21, 2012, which means faculty, instructional spaces and the departments must be packed and ready to go.
The balance of Human Ecology units including Centers, administration and projects will immediately follow - keep checking this blog for information and updates.